LOTTE Chemical disclosed on Sept. 17 that its board had stopped a KRW 77 billion (about $56 million) PET recycling project at Ulsan, South Korea, with about KRW 16.6 billion already spent (Net Zero Compare). Yazan Al Homsi, a Vancouver investor who holds a position in Aduro Clean Technologies through Founders Round Capital, backs a chemical recycler that was still engineering its first industrial plant in mid-October.
LOTTE stops, Eastman waits
LOTTE Chemical approved the Ulsan program in 2021. It planned a 45,000-metric-ton depolymerization plant to feed a 110,000-metric-ton chemically recycled PET line, and in 2022 it ran about 4,200 metric tons of trial production. The company finished engineering design for the depolymerization plant. Construction of the main plant didn’t begin.
The board cited changing market conditions, a prolonged petrochemical downturn, and the company’s role in industry restructuring. The timetable had already slipped from 2024 to the end of 2027. Around the time of the decision, the board approved a KRW 600 billion injection into H&L Advanced, a joint venture with HD Hyundai Oilbank. Platts, part of S&P Global Commodity Insights, put food-grade recycled PET pellets in Southeast Asia at $1,235 per metric ton on Sept. 18. Trading was thin, Net Zero Compare reports. In 2022 LOTTE had set a target of more than 1 million metric tons of recycled and bioplastic products by 2030; its 2024 ESG reporting said those targets would be reset. Net Zero Compare reported on Sept. 22 that the finished recycled-PET equipment was expected to stay in place at Ulsan. Its analysis says weaker economics and restructuring are forcing “a more selective investment approach” at the company.
Construction of Eastman Chemical’s $1.2 billion plastics recycling plant in Longview, Texas, was pushed back by at least two years in August 2025, after the U.S. Department of Energy canceled federal funding for it (Chemical Processing). The plant had been due to open in 2028. A spokesperson said Eastman was “reassessing the project scope and timing” while it appealed, and the company said the new path would push out large capital spending on the second plant by roughly two years. Chief executive Mark Costa said Eastman was looking at three other sites for the capacity. The Texas plant was part of Eastman’s plan to expand the methanolysis process it already runs in Kingsport, Tennessee. The Kingsport plant was operating at the time.
Aduro’s cash and its cost estimate
In June, Aduro, where Yazan Al Homsi holds his position, closed a U.S. public offering and a private placement in Canada that brought in net proceeds of about C$28.9 million. By Aug. 31 its cash stood at C$65.7 million, up from C$38.3 million at May 31 (Aduro first-quarter results).
Aduro reported no revenue for the quarter, against C$44,500 a year earlier, and an adjusted EBITDA loss of C$2.73 million. It said its revenue comes from customer evaluation programs and isn’t recurring, so it varies with project timing.
On Aug. 19 Aduro picked Saipem, the Italian engineering group, for Early Works on its planned 10,000-metric-ton plant at Chemelot in the Netherlands. The initial scope was the process design package and the critical equipment. It also included utility integration and the capital cost estimate. Aduro said the project may move to front-end engineering design, subject to completing that phase, continued evaluation, and definitive agreements. The release’s own risk list names cost increases and the chance that the Saipem work stops at Early Works. In June Aduro named Jan Lemmens project director for the plant. He has more than three decades of European industrial experience.
A pilot campaign Aduro reported in June ran 47 hours straight on polypropylene recovered from waste plastics, and liquid hydrocarbons made up about 86% of the polypropylene fed to the reactor. A 75-hour run in September across three feed compositions of polypropylene and polyethylene yielded condensable hydrocarbons at 88.8% to 90.8%. The pilot data is passed to Saipem, the release says. In June Aduro also signed a non-binding agreement with the Dutch waste group Ortessa to evaluate a feedstock logistics center.
The number Al Homsi wants early
In his analysis of the Early Works stage, Yazan Al Homsi wrote: “I’d rather have the honest number early than a flattering one late.” (EdTech Innovation Hub) EdTech Innovation Hub published the account on Sept. 10, a week before LOTTE’s disclosure. He holds the position as an investor with no board seat or operating role at Aduro, the account says. It describes Early Works as closer to due diligence than to breaking ground. When it chose Saipem, Aduro said it would pay for that phase from existing cash and didn’t expect to need new financing.
Due diligence was part of Al Homsi’s work for more than a decade at PwC in the Middle East, along with M&A advisory and IPO preparation. He rose to director before founding Founders Round Capital in Vancouver in 2017.
Construction of LOTTE’s main plant didn’t begin. Aduro’s Oct. 16 results release described the Chemelot plant as planned, with Early Works under way. It didn’t give a capital cost figure for the 10,000-metric-ton plant.